![]() |
||||||||||||||||||||||||||||||
![]() |
At a final cost of more than $110 million, Section A09 of the Lewistown Narrows is one of PennDOT’s largest and most complex construction projects. This section was the second largest construction project bid ever awarded by PennDOT, when the $104.36 million bid was awarded in 2004. (The largest single construction project bid prior to A09 was Route 202, Section 404, in Montgomery County at $104.86 million.) A09
is the third and final section of the nearly 10-mile long Route 22/322
Narrows reconstruction project in Central Pennsylvania's Mifflin and
Juniata counties. What
it took to build this section:
Begun in 2004, the four new lanes of Section A09 were open to traffic by December 14, 2007, far ahead of the original Fall 2008 schedule. Public amenities are to be completed in Spring 2008. At 6.65 miles in length, this section was one of the more complex projects to design and build because of the need to position the four-lane highway between the talus rock slope of the Shade Mountain and the Juanita River. For more than three decades, engineers considered ways to efficiently build a wider, modern highway while maintaining slope stability even after construction.
Some 40,000 core drillings, seismic refraction, and ground penetrating radar were used to analyze potential stability issues and evaluate construction alternatives. Seismic monitoring continued during construction.
The design
The
design minimized excavation along the talus rock slope.
All of the project design elements tie together to help ensure
"global" stability of the site. Part of the highway is
bifurcated, with the two westbound lanes elevated above the eastbound
(riverside) lanes for about three miles.
There
are more than four miles of retaining walls, including two mechanically
stabilized earth (MSE) walls, one of which is two miles in length and is
the longest MSE wall in the United States and the second largest in the
world. There are nine
reinforced concrete retaining walls along the riverside totaling 8,280
feet. There are also more than 46 miles of remediation pipe piles – piles embedded into the bedrock and filled with cement grout to add slope stability and also to counteract the weight of the completed highway. These piles are installed between the new highway lane areas and along the river's edge. Construction included two bridges, 55 feet and 290 feet long, both over Macedonia Run, and three box culverts totaling 486 feet. There are 51,000 feet, or 15 miles, of H-piles in project walls and bridge foundations.
The
completed highway has two 12-foot-wide lanes in each direction with
10-foot outside concrete shoulders. Inside shoulders vary from four
to nine feet. The completed
median area includes concrete glare screen barrier, where the median is narrow, and in other areas there is earth median, which
varies from 45- to 84-feet-wide. Special
traffic provisions One lane of traffic in each direction was maintained throughout the project using combinations of the two-lane, existing roadway; temporarily widened portions of the highway; temporary crossovers and roads; and the newly-built lanes as the project progressed. Frequent
traffic alerts were issued and also posted on this site.
(See Narrows traffic alerts page.)
Traffic
updates are also posted on message boards as well as highway advisory
radio (16.40 AM).
Environmental
Considerations Because
of wetland impacts, a wetlands mitigation area was created in Lack
Township, Juniata County. (See Section A11.)
There also was compensatory mitigation in Oliver Township, Mifflin
County, done under Section A10. There
are bass and trout in the streams and river. Work
at Horning Run, Macedonia Run, Roaring Run and two tributaries was timed
to minimize impacts on both wild and stocked trout.
A causeway was built along the river as a platform to construct a concrete retaining wall along the river for the eastbound lanes. Special provisions, such as working downstream to upstream to keep the water clearer, helped minimize impacts to fish and turtles. Other
measures to protect fish habitat included putting native rock in place;
dropping and anchoring some trees in the river; and placing fish baffles
in the box culverts. The
causeway was left in place to provide ongoing habitat.
During causeway construction, a herpetologist or reptile expert was on site to catch or chase away any turtles. There are several turtle species in the area, including the Wood Turtle. That turtle is not considered endangered in Pennsylvania, but is endangered in some other states.
Trees and vegetation were not disturbed if it wasn’t necessary. The endangered Wild Senna wildflower was protected with fencing during construction. Encountering
snakes, such as Timber Rattlesnakes and Northern Copperheads, is a
possibility when constructing a highway in this setting.
How snakes are protected under the Pennsylvania Fish & Boat
Code was included in special crew training, as was snake identification
and first aid procedures. Some
of the crews wore snake boots or chaps for additional protection, and
Lewistown Hospital stocked anti-venom in case someone is bitten.
Recreation,
History & Education The
Pennsylvania Canal and the Canal House, built in 1860, are special
features in the area. As
much of the canal as possible is being preserved. The Canal House structure was saved for future conversion to
a museum/visitor center. As one of the last construction phases, part of the canal towpath will become a 1˝ mile-long trail along the Juniata River between the new Canal Park and a new fishing boat access area. When completed in Spring 2008, it will feature an overlook above the canal lock.
The new Macedonia Run Canal Park will have
a picnic area, parking, and information kiosks.
Along the river will be a parking area, a boat launch, information
kiosks and an access area for people who are physically challenged. The
A09 project team
|
|||||||||||||||||||||||||||||